Skip to main content
White RavenIT Consultant Ltd

Finance & Banking

The migration we advised against — and the one we delivered

A workload-by-workload disposition assessment that stopped two of three planned migrations and cut projected three-year run cost by 31%.

Engagement

Client
A UK challenger bank
Sector
Finance & Banking
Location
United Kingdom
Completed

Results

What changed

  • 31%

    Three-year cost reduction

    Against the original plan

  • £2.1m

    Avoided spend

    From two cancelled migrations

  • 61

    Workloads migrated

    Across nine waves

  • 0

    Rollbacks required

    In production cutover

The challenge

What we were working against

The bank had board approval to move its remaining on-premises estate to public cloud within eighteen months. The business case had been built at platform level rather than per workload, and nobody had modelled the licensing implications of moving a heavily-licensed core database, or the egress cost of a reporting platform pulling nightly from a system that was staying put.

The approach

What we actually did

In sequence, including the parts that happened long before anyone touched hardware.
  1. 01

    Assessed all 84 workloads individually on cost, latency, data residency, licensing and operational fit rather than accepting the platform-level case.

  2. 02

    Built a three-year TCO model per workload comparing migration, replatforming and staying on refreshed on-premises hardware.

  3. 03

    Identified two workloads — the core database and the nightly reporting platform — where migration increased three-year cost by a combined £2.1m.

  4. 04

    Designed a governed Azure landing zone with policy, identity and network baselines defined as infrastructure as code.

  5. 05

    Migrated the remaining 61 in-scope workloads across nine waves with rehearsed cutovers and documented rollback at each stage.

They told us not to migrate two of our three target workloads, with the TCO model showing why. That single piece of advice paid for the whole engagement, and it is the reason we trusted them with the third.
David OkonkwoChief Technology Officer, a UK challenger bank

Services used

What this programme drew on

  • Consulting

    Cloud & Digital Modernisation

    Cloud migration, hybrid architecture and cost optimisation for organisations that need a business case, not a manifesto.

  • Consulting

    IT Consulting & Advisory

    Independent technology strategy, architecture reviews and roadmaps that tie every pound of IT spend to a business outcome.

More work

Other programmes

Client identity is withheld under the confidentiality terms of the engagement. Figures are as reported at programme close and can be substantiated under NDA on request.

Similar problem

Recognise any of this?

If the shape of your programme looks like this one, we have almost certainly hit the failure modes already. Let us save you the discovery.