940-site EPoS and network refresh across eleven countries

Replacing end-of-life point-of-sale and branch networking across 940 stores in fourteen months, without closing a single store for a day.

Engagement

Client
A pan-European grocery group
Sector
Retail & E-Commerce
Location
Eleven countries, EMEA
Completed

Results

What changed

  • 940

    Sites completed

    In fourteen months

  • 98.6%

    First-time-right

    No return visit required

  • 0

    Trading hours lost

    Across the whole programme

  • 11

    Suppliers consolidated

    Into a single contract

The challenge

What we were working against

The client's point-of-sale estate was running on hardware two years past end of support, on a branch network that could not carry the new payment platform. Eleven incumbent suppliers each covered a subset of countries with different SLAs, different reporting and no consolidated view of progress. A trading freeze from mid-October to early January removed a quarter of the delivery calendar.

The approach

What we actually did

In sequence, including the parts that happened long before anyone touched hardware.
  1. 01

    Established a single programme office with per-site readiness gates and a weekly burn-down shared with the client's steering group.

  2. 02

    Surveyed every site remotely first, then physically for the 22% that returned ambiguous data, producing a readiness matrix before any hardware was ordered.

  3. 03

    Pre-staged, imaged and asset-tagged all 940 EPoS sets and branch routers in two regional facilities, so on-site work reduced to a two-hour swap.

  4. 04

    Scheduled installations outside trading hours in eighteen-site weekly waves, with the old equipment collected on the same vehicle for certified disposal.

  5. 05

    Ran the trading freeze as planned downtime for the programme, banking four weeks of contingency before it rather than hoping for it after.

Nine hundred and forty sites in fourteen months, across eleven countries, and the weekly dashboard never once told us something we later found out was wrong. That is rarer than it should be.
Tomás AlvarezProgramme Director, a European grocery chain

Services used

What this programme drew on

  • Operations

    IT Rollouts & Deployment Programmes

    Multi-site hardware and software rollout programmes run to a fixed schedule with per-site sign-off and consolidated reporting.

  • Infrastructure

    Network Infrastructure & Structured Cabling

    Design, installation and certification of structured cabling, comms rooms and campus networks — delivered to standard, on a plan.

  • Operations

    IT Asset Management & Disposition

    Asset tracking through life and certified, auditable disposal at end of life — GDPR, WEEE and NIST 800-88 compliant.

More work

Other programmes

Client identity is withheld under the confidentiality terms of the engagement. Figures are as reported at programme close and can be substantiated under NDA on request.